Curtis Consulting of West Point was awarded a $28.5 million contract by the [[Commonwealth Transportation Board]] at their meeting on [[July 19]], [[2019]]. <ref>{{cite web|title=Albemarle County Design-Build Projects|url=https://www.virginiadot.org/projects/culpeper/albdesignbuild.asp|author=|work=Website|publisher=Virginia Department of Transportation|location=|publishdate=|accessdate=August 17, 2019}}</ref>
Curtis Consulting of West Point was awarded a $28.5 million contract by the [[Commonwealth Transportation Board]] at their meeting on [[July 19]], [[2019]]. <ref>{{cite web|title=Albemarle County Design-Build Projects|url=https://www.virginiadot.org/projects/culpeper/albdesignbuild.asp|author=|work=Website|publisher=Virginia Department of Transportation|location=|publishdate=|accessdate=August 17, 2019}}</ref>
The project has a total budget of $3.8 million. Engineering is budgeted at $850,000, right of way is budgeted at $500,000 and construction is budgeted at $2.45 million.
==Project purpose==
"This project will construct a quarter-mile, two-lane road to connect Rio Mills Road to the recently completed Berkmar Drive Extended. The work will include a sidewalk and shared-use path that connects to the bicycle and pedestrian facilities on Berkmar Drive Extended."


{{clear}}
{{clear}}
Line 15: Line 21:
==External Links==
==External Links==
*[https://www.virginiadot.org/projects/culpeper/albdesignbuild.asp VDOT project site]
*[https://www.virginiadot.org/projects/culpeper/albdesignbuild.asp VDOT project site]
*[https://smartportal.virginiahb2.org/#/public/applications/2018/hb2/view/F2-0000001408-R02 Smart Scale Application]
*[https://paptprd.blob.core.windows.net/scorecards/F2-0000001408-R02.PDF Smart Scale Scorecard]

Revision as of 22:31, 17 August 2019

The Rio Mills Road/Berkmar Drive Connection is a planned transportation improvement planned by the Virginia Department of Transportation that is one of six Albemarle County Design-Build Projects combined into one contract.

Curtis Consulting of West Point was awarded a $28.5 million contract by the Commonwealth Transportation Board at their meeting on July 19, 2019. [1]

The project has a total budget of $3.8 million. Engineering is budgeted at $850,000, right of way is budgeted at $500,000 and construction is budgeted at $2.45 million.

Project purpose

"This project will construct a quarter-mile, two-lane road to connect Rio Mills Road to the recently completed Berkmar Drive Extended. The work will include a sidewalk and shared-use path that connects to the bicycle and pedestrian facilities on Berkmar Drive Extended."


Timeline

  • July 19, 2019: CTB award scheduled as part of larger design-build project


Streetcar-photo-sim.jpg This Transportation-related article is a stub. You can help cvillepedia by expanding it.

References

  1. Web. Albemarle County Design-Build Projects, Website, Virginia Department of Transportation, retrieved August 17, 2019.