Georgetown Road: Difference between revisions

From Cvillepedia
Jump to navigation Jump to search
(New page: {{Infobox Transportation | name =Georgetown Road | photo = | caption = | status ={{planned}} <!--ABOVE USE:{{proposed}},{{planned}},{{underway}},{{complete}},or {{canceled}} --> | meeting ...)
 
mNo edit summary
Line 22: Line 22:
==Notes==
==Notes==
<references/>
<references/>
{{DEFAULTSORT:LAST, FIRST NAME}}
<!--ONLY USE for personal names for sorting purposes. Otherwise remove this field-->
[[Category: Transportation Matrix]]
[[Category: Transportation Matrix]]
<!--Enter categories to right of colon and repeat as needed. See special categories page for ideas. If you can't think of a category, remove this field.-->

Revision as of 14:21, 7 July 2009


Georgetown Road

Planned

Project Overview

Improve pedestrian and vehicular safety by making road improvements and adding multi-modal facilities (bike lanes and improved sidewalks).
Cost $3,018,300
Sponsor VDOT
Next meeting March 24, 2009 Public Hearing at Albemarle High School

Status Update

VDOT reported in November 2007 that right of way acquisition phase will begin in December 2008 with an estimated advertisement date of early 2011. The project has been drastically scaled back from its original plan. In July 2007, VDOT's Utility Section will determine if utility relocation can be scaled back. Project may be pushed back further due to continued reductions in state and federal transportation revenues. Priority on County’s Secondary Six-Year Improvement Program.

Website Project website
Contact Greg Krystyniak, Project Manager, Location & Design Section, VDOT Culpeper District

Map