Dairy Road Bridge

From Cvillepedia
Jump to navigation Jump to search

The Dairy Road Bridge crosses the Route 250 Bypass to connect Dairy Road to Grove Road. It was constructed in 1954[1] as part of the construction of the bypass.[2]

In 2017, the Dairy Road Pedestrian Bridge was built to provide a parallel bicycle/pedestrian pathway across 250. At that time the vehicular bridge received concrete repairs, joint replacement, and epoxy overlay, along with the removal of the sidewalk attached to the bridge.[3]

Replacement

In 2019, Mid-Atlantic Engineering completed a study on potential options to rehabilitate or replace the aging bridge.[4]

VDOT awarded $7,210,664 in State of Good Repair funding to replace the bridge in August 2021, which was appropriated by City Council on April 18, 2022.[5]

On January 5, 2023, the city announced a plan to use a Design-Build process to procure the bridge replacement.[1] A contract was awarded to A. Morton and Associates on February 23, 2023.[6]

A design public hearing was held on May 22, 2025.[7] The selected design and construction plan involve a one-year closure of the crossing.

As of January 2026, $12.62 million was allocated for the project in the VDOT Six-Year Improvement Plan.[8]

References

  1. 1.0 1.1 Web. Charlottesville to alter process for replacing Dairy Road Bridge, Sean Tubbs, News Article, Town Crier Productions, January 6, 2023, retrieved 2026-01-14.
  2. Web. State Asks Bids on By-Pass Link, Daily Progress, Lee Enterprises, March 27, 1953, retrieved 2026-01-14. Print. page 1.
  3. Web. Dairy Road work will mean closures, Daily Progress, Lee Enterprises, October 1, 2017, retrieved January 7, 2023.
  4. Web. Dairy Road SGR Cost Estimates, Mid-Atlantic Engineering Group, December 9, 2019, retrieved 2026-01-14.
  5. Web. Agenda for April 18, 2022 Charlottesville City Council, City of Charlottesville, April 18, 2022., retrieved 2026-01-14.
  6. Web. City awards design-build contract for Dairy Bridge replacement, Sean Tubbs, News Article, Town Crier Productions, February 25, 2023
  7. Web. Charlottesville to hold public hearing on Dairy Road replacement bridge, Sean Tubbs, News Article, Town Crier Productions, July 14, 2025, retrieved 2026-01-14.
  8. Web. Six-Year Improvement Program – #SGR21LB DAIRY ROAD OVER RTE 250 BYPASS, Virginia Department of Transportation, January 2026, retrieved 2026-01-14.