1709 Jefferson Park Avenue is the working name for a 27-unit apartment complex planned for construction at the same address. It would replace an 8-unit building. City Council approved a special use permit on October 2, 2023. [1]
Timeline
- April 11, 2023 – Planning Commission holds preliminary discussion[2]
- September 12, 2023 – Planning Commission recommends approval of special use permit and critical slope waiver[3]
- October 2, 2023 – City Council approves special use permit and critical slope waiver[1]
- November 14, 2023 – Entrance Corridor Review Board approves Certificate of Appropriateness[4]
References
- ↑ 1.0 1.1 Web. Divided Charlottesville Council OKs JPA student-plex, Hawes Spencer, Daily Progress, Lee Enterprises, October 3, 2023, retrieved November 13, 2023.
- ↑ Web. Agenda for April 11, 2023 Charlottesville Planning Commission, City of Charlottesville, April 11, 2023., retrieved 2025-01-28.
- ↑ Web. Agenda for September 12, 2023 Charlottesville Planning Commission, City of Charlottesville, September 12, 2023., retrieved 2025-01-28.
- ↑ Web. Agenda for November 14, 2023 Charlottesville Planning Commission, City of Charlottesville, November 14, 2023., retrieved 2025-01-28.